Stoke Gifford Journal > Major Projects > Stoke Gifford By-Pass
468x80 Local

Stoke Gifford By-Pass

Planning permission for the The Stoke Gifford By-Pass, officially known as the Stoke Gifford Transport Link (SGTL), was granted in September 2013.

Work on the £14 million scheme began in summer 2015, with completion expected in 2017 (the projected opening date is currently September 2017).

Stoke Gifford Transport Link (Stoke Gifford By-Pass).

Click on image to enlarge. Please note that this diagram is from an early consultation document and may not accurately represent the approved plans (see below).

The new by-pass will be used by the North Fringe to Hengrove Package bus rapid transit scheme, part of the planned MetroBus network

Contractor

Alun Griffiths, MetroBus contractors in The Stokes, north Bristol.

Alun Griffiths (Contractors) Ltd have been awarded the contracts for the Stoke Gifford Transport Link (SGTL) and works at Bradley Stoke Way and Coldharbour/Stoke Lane.

Alun Griffiths have written to residents affected by the works. The letters provide contact details for their Community Liaison Officer, who will answer queries relating to the construction works.

Alun Griffiths have set up a phone number for anyone with questions about the construction works. The number is manned between 8am and 6pm Monday to Saturday. Outside these hours, please leave a message and your call will be returned. The number is: 0845 86 22 327.

For more information, visit the contractor’s community website for the North Fringe to Hengrove Package MetroBus project.

To send a compliment, query or complaint, visit the Contact the Site page.

Read more: Introducing the contractor for MetroBus work in The Stokes (Bradley Stoke Journal)

Photo: Construction of the by-pass under way near the Parkway North Roundabout.

Timeline

6th February 2017
Closure of a section of Hambrook Lane for an estimated two weeks

1st August 2016
Hambrook Lane reopened

28th/29th May 2016
New railway bridge lifted into position near Curtis Lane

2nd September 2015
Closure of a section of Hambrook Lane for an estimated 38 weeks

Progress reports

March 2017 (Bradley Stoke Journal magazine, March 2017)

The work in this area is shared across three contractors, with Griffiths having responsibility for the roadworks. There are two bridges, one has been handed to Griffiths some months ago by Network Rail and good progress has been made with the road here. The other bridge (over the Ham Brook) is still in possession of the remaining contractor and Griffiths await access to complete the roadwork.

We anticipate that all drainage work will be completed during April and May, as well as laying the road base, binder and surface course from Parkway North Roundabout along to the Network Rail bridge and down to the Hambrook Lane junction.

Work will commence moving fill materials in readiness for filling the ground level on the approach to Ham Brook Bridge from the north and south side to make progress in laying of the road over it. Earthwork will continue to shape the verges and work has commenced and is ongoing on the sound attenuation bund protecting the housing that borders the stretch between the Network Rail bridge and Great Stoke Way. This will later be topped with a two-metre-high acoustic fence.

Final surface course and road markings will be taking place in early April, from the A4174 up to the Oxleigh Way junction and from the north of the new Ham Brook bridge up to Hambrook Lane.

The Ham Brook bridge and the approaches approximately 300m long on either side of it will be surfaced, along with all associated works, once it has been handed over to Alun Griffiths.

A series of short duration closures of Hambrook Lane will be required for final surfacing and anti-skid treatment. These will last for a total of no longer than five days over a few weeks in May and June.

February 2017 (Bradley Stoke Journal magazine, March 2017)

The work in this area is shared between three contractors, with Griffiths having responsibility for the roadworks. There are two bridges; one was handed to Griffiths some months ago by Network Rail and good progress has been made with the road here. The other bridge (over the Ham Brook) is still in possession of the remaining contractor and Griffiths await access to complete the roadworks. Griffiths works are well on programme and we are currently forming the new access off Parkway North Roundabout.

Hambrook Lane reopened a week earlier than advertised following lane widening and kerbing. A further (and final) one-week closure will be required in May/June for resurfacing and road marking. Works along the A4174 Ring Road are 95 percent complete awaiting final surfacing at the tie-in and within the central reserve island.

January 2017 (Bradley Stoke Journal magazine, February 2017)

Hambrook Lane will be closed initially for two weeks from Monday 6th February to allow the construction of access tracks and the widening of the lane itself. A final closure for one week will be advertised in due course once surfacing dates have been agreed.

The section from Parkway North Roundabout to the Network Rail bridge is now fully under way. We are taking advantage of the dry weather to press on with the drainage operations. Earthworks will recommence in February.

The carriageway from the Network Rail bridge to the A4174 is now largely complete with landscaping and planting works well advanced.

The Ham Brook Bridge section, being constructed by a separate contractor, has not yet been handed over to Griffiths, which has prevented us from making progress with the road at this point.

At the A4174 junction, second phase works (including kerbing, traffic signal works and surfacing) will continue throughout February.

December 2016 (Bradley Stoke Journal magazine, January 2017)

A4174 – for a period estimated as four weeks, from early January to early February, we shall be starting on the second phase of signalisation work on the east and westbound carriageways of the junction of the link road with the A4174. This will involve lane closures in both directions but only for evening work outside of peak hours (from 6pm to 1am at the latest). Lighting towers will be erected and, each night, a short section of road will be worked on.

Hambrook Lane will be closed from early February for three weeks to conduct second phase works for construction of farmer’s access and lane widening. Advanced notice signage will be in place and diversions signposted (plans are also available online).

From Parkway North Roundabout to the new railway bridge – Thanks to unseasonably fine weather we have made excellent progress on the road construction in this area. Progress will continue with the hope of tarmacking the area in the spring.

July 2016 (Bradley Stoke Journal magazine, August 2016)

Hambrook Lane in Stoke Gifford will reopen on 1st August. This coincides with an order extending the 30mph area by a further 200 metres south-east of the existing 30mph signs near the junction with Curtis Lane. This is to reflect the new and future changing nature of the road in conjunction with the Stoke Gifford Transport Link for MetroBus being built.

The road has been closed since August 2015 to allow MetroBus to construct two new bridges, a new junction and a pedestrian and cycle path for the forthcoming Stoke Gifford Transport Link.

The narrow road was closed for nearly a year because it isn’t wide enough to accommodate construction works and traffic. Access for residents was maintained throughout the construction period.

The reopening of the road will alleviate congestion for motorists in the north of the city.

Work continues on the A4174 bus and 2+ lane closure westbound from J1 M32 and central reservation work. Traffic Management and barriers will then be installed on the westbound Lane 1, to allow works to commence on Tuesday 26th July until the end of August. Once this is complete, operations on the A4174 will be suspended until the Traffic Signals are commissioned in the winter.

June 2016 (Bradley Stoke Journal magazine, July 2016)

Jim Aitken of Alun Griffiths Ltd reports on the progress being made on the SGTL (known locally as the Stoke Gifford By-Pass):

Bristol Water have completed their work in the area of Hambrook Lane and it is now on programme to be reopened in July.

Works are ongoing to commence on tie-in with the SGTL on A4174. Initially we have closed the 2+ bus lane eastbound from Cold Harbour Junction toward the M32 Junction 1 to enable the new road construction, for approximately eight weeks.

Once completed, we shall then install traffic management on the west bound section of the A4174 from M32 Junction 1 to Cold Harbour Lane to complete the second side, again closing the 2+ lane and then moving into the central reserve area for approximately six weeks.

We hope to remove all traffic management on the A4174 by 16th September, having completed the work in hand.

Surfacing within main SGTL site is 60 percent complete, awaiting bridges to be handed over by Network Rail to enable earthworks to recommence.

Griffiths are soon to commence footways and traffic signal junctions at A4174 Maules Lane and Hambrook.

February 2016 (Bradley Stoke Journal magazine, March 2016)

  • Diversion of high pressure water main at A4174 to enable the construction of the new road junction at this location.
  • Installation of ground water attenuation blankets at Ham Brook to allow the construction of the Ham Brook bridge.
  • Testing/removal of contaminated material from Tudor Lodge, prior to excavation of a cutting to the new Network Rail bridge, which is planned to be installed in “early summer”.
  • Installation of a crane pad for construction of the new Network Rail bridge.
  • Diversion of a high-voltage Western Power cable to facilitate the tie-in of the new carriageway to Parkway North roundabout.
  • Establishment of a material storage area on (part of) Network Rail overspill car park, to alleviate traffic congestion on Parkway North roundabout.

More information and related links

Planning Applications (South Gloucestershire Council)

PT13/1529/R3F – Received 8th May 2013; Approved 24th Oct 2013

Construction of new road link (Stoke Gifford Transport Link), incorporating single carriageway highway, (with additional bus lanes where appropriate) footways and cycle ways. Construction of bridge over the South Wales – London railway line and construction of new bridge over the Ham Brook. Associated works and landscaping. | 15.85 Hectares Of Land Between Parkway North Roundabout At The Southern End Of Great Stoke Way And The A4174 Avon Ring Road To The North East Of UWE.

PT14/0600/R3F – Received 18th Feb 2014; Approved 23rd May 2014

Construction of new road link (Stoke Gifford Transport Link), incorporating single carriageway highway, (with additional bus lanes where appropriate) footways and cycle ways. Construction of bridge over the South Wales – London railway line and construction of new bridge over the Ham Brook. Associated works and landscaping. (Amendment to previously approved scheme PT13/1529/R3F including revisions to the vertical and horizontal alignment of the road of no more than 1.5m, revisions to Harry Stoke junction and Hambrook lane junction.) | 15.85 Hectares Of Land Between Parkway North Roundabout At The Southern End Of Great Stoke Way And The A4174 Avon Ring Road To The North East Of UWE.

Stoke Gifford By-Pass Stories in The Journal

Location Plan

Location plan of the Stoke Gifford Transport Link (SGTL).

Click the image above to view the location plan at full size.

UK_Restaurants_300x250Advertising in the Stoke Gifford Journal

The Bradley Stoke Journal magazine - your MONTHLY local newspaper.
Office accommodation at Courtyard Offices, Bradley Stoke, Bristol.
Chiropractor, Patchway, Bristol BS34.